——-Zesco is set to construct a 66kv overhead line from Chambishi Copper Smelter in Kalulushi to a proposed substation site in Chingola.

ZESCO Environmental Specialist Kabamba Mbewe  confirmed this in an interview in Kalulushi district today.

 

This was when she and her team had a stakeholder consultative meeting at the District Commissioner’s Office.

Ms Mbewe said  her  utility company  will commence  the project  to meet the growing demand for power in Chingola district  due to increased social-economic activities.

She  said the line would cover the distance of Approximately 30 kilometres.

And  Kalulushi District Commission Kampamba Mulenga says she welcomes the development to the id the idea was welcome in the area